Bolo AI Agent· Promethean Energy
BK
Portfolio
Task order · TO-7

BSEE TO-7 · Lower & Upper Abandonment

17 wells · 6 platforms · BSEE Gulf of Mexico · $16.34M AFE · Last updated 31 May 2026

On ST 67 B (in transit) · Phase 2 — Lower T&A · Day 40 of plan
Platforms
2 complete · 2 underway · 2 to go
≈16% work complete
PM Danny Turner · Supt Ernie Boudreaux · 26 on board (POB)
Money · the leadership lens
Cash-flow position
+$2.1M
stays positive · tightest ~Aug

milestone receipts − invoiced expense

Apr 22May 11May 16May 27May 31Jun 20
milestone receipts invoiced cost
Margin & why
22.5% / 18.4%
Conflict

vs bid 17.5%

Phase · days planned → actualForecastΔ
GI 22 P · Lower T&A
8 → 5
$662K
$298K
GI 22 R · Lower T&A
7 → 5
$530K
$153K
ST 27 D · Lower T&A (partial)
9 → 4 (partial)
$777K
$465K

Driver: fewer days on early phases. But ~83% of modeled cost is still forecast — not yet banked.

Cost vs AFE
$2.29M of $16.34M

14% spent

Burn ~$90K/active day

Daily brief · May 31 · Report #30 (signed)
View all daily reports →
What happened

ST 67 B lower T&A complete; rigged down, off platform, in transit/demob. Crescent crew released — no wells cost today. Daily cost (vs ~$90K on active days).

24-hr look-ahead

Continue transit; prep ST 54 G mobilization.

Activity
MODM (mob/demob)RDN (rig down)ALGD (all good)
What changed / needs note

Report #30 signed & sent to BSEE. Today's actual is in the but not yet in the .

Cost to BSEE by account code · from the DPR cost report

Cost-to-date = BSEE-billable (vendor cost × ~1.23 markup). AFE = approved budget (BAC). AFE is live from the DPR; cost-to-date is illustrative until the latest signed DPR is connected.

AccountDescriptionCost to dateillustrativeAFEUsedReconciliation
WSR-0-100
Well Services (Crescent)largest
$861K
$6567K
13%
needs tickets
VES-0-100
Vessel Services
$548K
$4863K
11%
ties to DPR detail
COL-0-100
Company Labor
$331K
$2455K
13%
ties to DPR detail
MIS-0-100
Financial Assurance
$181K
$527K
34%
ties to DPR detail
DOS-0-100
Dock Services
$121K
$558K
22%
ties to DPR detail
SRT-0-100
Surface Rentals
$92K
$272K
34%
ties to DPR detail
LOG-0-100
Logistics & Air Transport
$54K
$443K
12%
ties to DPR detail
COM-0-100
Communications
$6K
$19K
31%
ties to DPR detail
Total
$2.29M
$16.34M
14%
Top 8 of 22 accounts shown
Milestones & billing
Next: ST 27 D partial
Billed to date $1.44M of $2.83M Lower-phase milestones
51%
MilestoneProgressPlannedBilledStatus
Lower Abandonment (Phase 2)
GI 22 P · Lower T&A
100%
$618K
$637K
Billed +$19K — confirm
GI 22 R · Lower T&A
100%
$773K
$800K
Billed +$27K — confirm
ST 27 D · Lower T&A
70%
$906K
Partial — D9 needs CTU
ST 67 B · Lower T&A
50%
$537K
In progress 50%
CO2 · ST 21 #81
0%
Submitted to BSEE
Upper Abandonment — forecast
Upper Abandonment (all)
$8711K
Forecast
Invoice/payment model: invoice ~20 days after cost, paid ~20 days after invoice.
Field tickets & vendors

Crescent ticket ↔ DPR reconciliation · POB vs labor hours · overtime flags (16-hr days)

Every ticket also builds your equipment/cost dataset for faster bids.

Schedule · this project
PlatformActualModel plannedStatus
GI 22 P
5/7 – 5/11
5/7 – 5/11
aligned
GI 22 R
5/12 – 5/16
5/12 – 5/16
aligned
ST 27 D
5/17 – 5/20
5/17 – 5/20
aligned
ST 67 B
5/21 – 5/27
6/3 – 6/7
model ~2 weeks behind actual

Model schedule is ~2 weeks behind actual on ST 67 B → milestone/cash timing off.

Cash position, account-code splits and schedule are illustrative; TO-7 milestone, margin and reconciliation figures are from the live files.

Sources: TO7 Financial Outlook · DPR · TO7 Milestones