BSEE TO-7 · Lower & Upper Abandonment
17 wells · 6 platforms · BSEE Gulf of Mexico · $16.34M AFE · Last updated 31 May 2026
milestone receipts − invoiced expense
vs bid 17.5%
Driver: fewer days on early phases. But ~83% of modeled cost is still forecast — not yet banked.
14% spent
Burn ~$90K/active day
ST 67 B lower T&A complete; rigged down, off platform, in transit/demob. Crescent crew released — no wells cost today. Daily cost (vs ~$90K on active days).
Continue transit; prep ST 54 G mobilization.
Report #30 signed & sent to BSEE. Today's actual is in the but not yet in the .
Cost-to-date = BSEE-billable (vendor cost × ~1.23 markup). AFE = approved budget (BAC). AFE is live from the DPR; cost-to-date is illustrative until the latest signed DPR is connected.
Crescent ticket ↔ DPR reconciliation · POB vs labor hours · overtime flags (16-hr days)
Every ticket also builds your equipment/cost dataset for faster bids.
Model schedule is ~2 weeks behind actual on ST 67 B → milestone/cash timing off.
Cash position, account-code splits and schedule are illustrative; TO-7 milestone, margin and reconciliation figures are from the live files.